Kerbs
- Purpose
Kerbs are used in heavily
trafficked areas to provide extra strength to the edge of
the carriageway. They also:
Prevent vegetation
encroaching onto the road
Act as a debarkation
line between the road and footway
Deter traffic from
mounting the footway
Provide a wall to
divert water run off into the gullies
Prevent the surfacing
materials on the road from spreading under load
Reinstatement
Kerbs or footway edge
restraints removed, displaced or damaged during excavation
works or otherwise must be replaced at the time of permanent
or interim repair. This is required to maintain the
structural integrity of the road and adjoining surfaces.
During excavation work care
must be taken to prevent unnecessary removal or disturbance
of the kerbs. Any concrete bed that is undercut during
excavation will be difficult to reinstate and remedial work
should be carried out, this may require the removal of any
undercut bedding and kerbs.
Care needs to be taken where
natural stone kerbs have been used as replacements are
expensive and not easily sourced. Damaged natural stone
kerbs may be sourced from the local authority if stocks are
held for such an eventuality.
Kerbs and edge restraints
must be replaced as existing to maintain the appearance of
the surface.
Concrete used as bedding or
backing must conform to Clause 1602 (Class E). This can be
mixed on-site using a 1:3:6 mix ratio.
There are two methods of
laying or re-laying kerbs and edge restraints.
Method
One - Wet Bed
This method is more suitable
for reinstatement purposes. A bed of concrete is laid so
that it is 20 - 40mm proud and the kerbs knocked down level
with the adjacent line of kerbs. This bed of concrete should
be laid on the sub-base. A backing, as existing, is then
placed using the same quality concrete as the bed, where
paving is to be laid care should be taken to prevent the
concrete backing being too high and encroach on the laying
of the paving. Once the concrete has set any adjacent works
may commence.
Method
Two - Dry Bed
A bed of concrete is laid
that will allow the kerbs to be laid on a bed of mortar
about 15mm thick once the concrete has set. In some
situations an epoxy resin may be used in place of mortar.
Backing is then laid in the same way as the wet bed method.
The
tolerances permitted are + or - 6mm between adjacent kerbs,
but in high amenity areas this may be unacceptable. Where
ever possible the kerbs should be flush along the top and
face of the kerb line.
Any gaps between the kerbs
are filled with fine concrete or a mortar mix.
Edge restraint are laid in
the same way as kerbs.
Any reinstatement within
250mm of adjacent kerbs of edge restraint must be removed
and included within the resurfacing of the pavement.
Any channel blocks or other
special feature must be replaced at the time of
reinstatement.
The interface between kerbs
must be treated with joint sealant prior to resurfacing to
prevent the ingress of water. Highway Ironwork
Any fixed feature such as
ironwork must must be reset if disturbed during excavation
work or otherwise. If the ironwork has been damaged it
should be replaced with a similar type and design. Any
ironwork that is disturbed or damaged should be notified to
the owners.
Where any reinstatement is
within 250mm of any ironwork the area between should be
trimmed back to include it at the time of resurfacing.
Care must be taken not to
allow any compaction equipment to come into contact with any
ironwork during reinstatement as it could dislodge it and
break the mortar bed or underlying block work.
The tolerances given on
ironwork are + or - 6mm to the adjacent surface, gullies may
be up to -15mm. Where the ironwork is within a footway there
should be no significant trip that would put pedestrians at
risk.