|
|

|

|
Note:-
New BS EN 12591
Wearing Course = Surface Course; Base Course = Binder
Course; Roadbase = Base
By employing sound
excavation methods the risks of subsequent reinstatement
failure can be avoided. Below are some basis principles to
adopt.
Safe Excavation
The Health and Safety Executive has produced and recently
revised guidance for excavation work HSG (47), this guide
applies whether excavation work is on the highway or
otherwise. This guide should be followed as failure to do
so has lead to injury, death and prosecution. Reference
can also be made to Construction Health Safety and Welfare
Regulations 1996.
Summary of HSG (47)
Avoiding Danger From Underground Services
Below are the main
principles to adopt before excavation work commences.
- A Suitable and
sufficient assessment of the risks involved must be
undertaken and safe systems of work made clear to
those involved in the works
- Utility plans showing
the location of underground services must be obtained
- The plans need to be
interpreted by a competent person
- Where the plans
cannot be interpreted the utility company must be
consulted for advice
- A cable locator must
be used to mark the position of the services up to 1
metre outside the excavation area
- Where an unknown or
unmarked service is located it must be reported to the
likely utility company, tracing it to a source will
also help in identifying it
- Local authority plans
showing drainage, fowl water, etc must also be
obtained
- Suitable excavation
equipment should be used and trial hole dug to confirm
the location of the services
- Mechanical excavation
should not be used closer than 0.5 metre to the
service
- In the event of a
service being damaged the utility company must be
informed. The area may need to be evacuated and the
emergency services called where there is a risk to
life or property
- If excavating through
any concrete any service lines should be made safe
- Exposed services must
be supported and protected to prevent movement and the
risk of damage by other works
In addition to the above
summary of HSG 47 the risk of trench collapse must be
continually assessed. Past legislation suggested that when
an excavation reached 1.4 metres the use of trench support
is required. In the light of recent changes to legislation
the depth is irrelevant as a trench in poor ground or high
water tables may also pose a risk.
Personnel working in deep
trenches near the traffic lanes are also at risk from
carbon-monoxide poisoning and steps should be taken in
accordance with the Confined Spaces Regulations to ensure
that no person is put at risk.
The time between opening
the highway and reinstatement should be kept to a minimum
to prevent the subgrade and exposed faces from drying out.
The surface material should
be cut with a pavement saw cleanly and vertically. the use
of a breaker should be avoided as this can damage the
surface edge and sometimes cause undercutting.
The sides of the excavation
should be vertical and the bottom flat to allow for even
compaction during reinstatement.
Ground and surface water
must be controlled by pumping or diverting. Water left in
the trench when reinstatement is carried out will cause
the material to 'sponge' and full compaction difficult to
achieve.
Excavated materials for
re-use must be either removed for storage or adequately
protected on-site to prevent drying, wetting or
contamination. Material for disposal should be removed
from site as soon as possible. Material must be kept at
least 1 metre from the trench to prevent overloading the
unsupported sides.
The trench should be made
large enough to accommodate the work activities
undertaken.
A trench by virtue of its
nature may be defined as a confined space, reference
should be made to the Confined Spaces Regulations and safe
working practices employed on site.
There should be adequate
and safe means of access and egress into the trench.
Deep excavations may need
covering with steel sheets or a more rigid barrier
provided to prevent unauthorised access or where the risks
of falling in are high.
|
|
|
|
|